Minton Rd and Waco Blvd Paving Project Begins
Curated by
gaume
3 min read
699
The City of Palm Bay is set to begin a major paving project on Minton Road, requiring a full road closure between Jupiter Blvd and Malabar Rd from July 8 to July 30, 2024. Ranger Construction, the contractor for the project, will perform extensive roadwork using Full Depth Reclamation (FDR) to improve the infrastructure of Minton Road and Waco Blvd.
Minton Road Closure Details
- Minton Road will be fully closed between Jupiter Blvd and Malabar Rd from July 8, 2024, to July 30, 2024, 24 hours a day.1
- Detours and traffic adjustments include turn lane closures on westbound Malabar to southbound Minton, outside lane closure transitioning to a through lane closure at the traffic light on southbound Minton approaching Malabar, and turn lane closure on eastbound Jupiter to northbound Minton.1
- Changeable Message Signs (CMS) and channelizing devices have been placed by Ranger Construction to guide traffic and ensure safety. Motorists should use caution and follow posted detour routes.1
1 source
Full Depth Reclamation Project
The Minton Road and Waco Blvd paving project utilizes Full Depth Reclamation (FDR), a sustainable method that recycles existing pavement materials to create a stronger, more durable road base.
1
FDR involves pulverizing the existing road to a depth of 12 inches on Minton Road and 8 inches on Waco Blvd, then stabilizing the material to form a new foundation.1
A fresh layer of asphalt will be applied to create a smooth driving surface.1
This environmentally friendly process enhances the structural integrity of the roadway, leading to longer-lasting results while reducing waste and the need for new raw materials.1
1 source
Contractor and Bid Information
Ranger Construction secured the contract for the Minton Road and Waco Blvd paving project with a total bid of $2,810,577.77, which includes $1,222,539.55 for Minton Rd and $1,588,018.22 for Waco Blvd.
1
The city selected Ranger Construction after a thorough verification process and contract discussions to ensure they can deliver quality work within the project's budget and timeline.1
The competing bid from Timothy Rose Contracting Inc. totaled $3,394,423.80, with $1,497,810.95 for Minton Rd and $1,896,612.85 for Waco Blvd.1
1 source
Community Coordination and Safety
- Ranger Construction will closely coordinate with Columbia Elementary School and local residents to minimize disruption during the project.1
- Residents will receive timely updates on any changes to the construction schedule.1
- For questions or concerns about the lane and road closures, residents can contact Public Works customer service at (321) 952-3438.1
- The Palm Bayer is committed to providing the community with real-time updates on the Minton Road and Waco Blvd paving project through their Facebook, X (Twitter), and Reddit channels.1
1 source
Related
how will the community be informed about the construction progress
what measures will be taken to ensure safety during the construction
how will the construction affect local businesses and residents
what are the potential environmental impacts of the FDR process
how will the city handle any unexpected issues during the project